Sr No | Particular | Sequence of Activity |
1 | Quote to customer of his Inquiry as per his requirement | Quotation |
2 | Drawing,Sample and order with Schedule are Received from Customer | Order / Planning |
3 | Job card release/Whole Designing And detail designing and preparing parts drawing | Design / Release |
4 | Order to vendor for raw material requirement or order to customer for arrange | Raw Material Order |
5 | Received raw Material(casting or bar or block) from customer / outside vender source | Raw Material Inward |
6 | Checked raw goods and if require prepare pre-machining drawing | Inspection |
7 | Send it to vendor or inhouse convensional shop for pre-machining/part making with drawing | Premachining (Conventional Shop) |
8 | Received it to VMC/CNC shop and checked pre-machining dimension | CNC Shop / Inspection |
9 | Prepare Programme and inspection report with set up sheet and clamping | Programming/Setting |
10 | Inspect durring machining after each progremme | In process Inspection |
11 | After completed VMC/CNC process send it for final inspection | Inspection |
12 | Send it to Convensional shop for Assambly(all part from vmc and conventional and readymade) | Assambly |
13 | After Assambly completed polished goods | Polishing |
14 | After polishing and assambly inspect all throughly. | Inspection |
15 | If require, trial all assambly | Trial |
16 | Packing in boxes for despatch | Packing |
17 | Dispatch with require Document | Dispatch |